With first phase of these works now fully completed it is time to outline what’s next.
With the opening of the new putting green adjacent to the hitting nets by the 3rd tee, works on remodelling and rebuild the large putting green near the 7th have begun. These works will see the excavation of the area, the laying of a new irrigation ring and sprinklers, and the construction, to USGA specifications, of a larger and more interesting putting green. In parallel to this, we will be carrying out much the same works to the short game area at the range. Again, a larger green with a new bunkering system, will be built to USGA specifications.
The works are scheduled to take several weeks, and we will be flying in a specialist shaper to complete the green construction.
Once the new greens are ready, it will be seeded with bent grass, and it is envisaged that the green will require 10-12 weeks to fully grow in.